Property Update

  • Hawkins (construction): The work on the lift continues.  Next week there will be an external cover placed over the structure (shrink wrapped). On Tuesday work will commence behind the hoardings opening up the walls in readiness for the lift.  There may be some noise during the day.  The lift will be craned onsite on Saturday 18 December.

         Hall wall – work on the temporary wall in the hall will continue throughout the week.  

        Very noisy work times are 7.00 am to 8.30 am (9.30 am on Wednesdays )  and then in the afternoons 3.30 onwards.  Thank you all for your understanding.

  • Ceres (deconstruction): The rubbish chute will continue to be used next week after 3.30pm.

 

  • Atrium closed from 14 December: The Atrium will be closed from 14 December – the scaffolders will be in the Atrium putting up the scaffolding in preparation for removing the linkways. If the linkways are out of action during this day they will be barriered off at the time.